Track replacement closes tram line to Wimbledon for 10 days

Disruption: the tram network is subject to strikes and closures until the end of August

As part of Transport for London’s programme to renew the infrastructure of London Trams, work to replace nearly half a mile of track between Wimbledon and Therapia Lane will be taking place from next Monday, August 22, until Wednesday August 31.

No tram service will run between Wimbledon and Therapia Lane while approximately 700 metres of track is replaced.

“This work will ensure tram reliability is maintained and services can run smoothly,” TfL says.

During these works:

“I would like to thank customers for their patience and understanding while this work takes place,” said Mark Davis, TfL’s general manager for London Trams.

“This vital maintenance will help improve reliability and ride quality for our customers. Please plan ahead and allow plenty of time for your journey.”

TfL says that during the 10-day closure, “Work will take place 24 hours a day to ensure customer disruption is kept to a minimum.”

Other works will also be undertaken – platform painting and paving, drainage works, fencing repairs and vegetation removal – “to reduce the need and frequency of future closures”, TfL said.

Strike action: the next industrial action to affect the tram network is this Friday, Aug 19

Hopper fares continue to be available for adult pay-as-you-go customers, giving unlimited journeys on buses and trams for £1.65 made within one hour of touching in. This means customers should pay no more than normal to complete their journey during these works.

Information regarding these temporary changes and travel advice will be displayed at local tram stops and customers are encouraged to plan ahead and consider alternative travel options. For status updates, live bus arrivals and to plan a route visit https://tfl.gov.uk/statusupdates/travel-tools