Critical state: there is already a weight and speed restriction on the A232 Croydon Flyover, but TfL says it may have to close altogether unless it undergoes repairs urgently
TfL wants government funding for £30m repair project which could take three years to complete
The A232 Croydon Flyover may have to close within four years unless it undergoes millions of pounds’ worth of repairs.
Reports from Transport for London, which is responsible for the road, say that the 1960s-built concrete and steel structure is “life expired”, with much of the Croydon Flyover “in a critical state of deterioration”.
About 40,000 vehicles use the Flyover each day.
Inside Croydon has been reporting the dire state of disrepair of the Croydon Flyover for more than four years. Six-monthly TfL engineering checks conducted on the structure show deterioration at an increasing rate, as water ingress has rusted the steel and left its concrete crumbling. The six-lane urban motorway, built between 1965 and 1968, is already subject to a 30mph speed limit and has a 18-tonne weight restriction on vehicles.
TfL is seeking £30million funding from government for repairs on the major east-west route from the town centre to the Purley Way.
The Croydon Flyover is one of six London structures given the highest priority for repairs by TfL.

Off-limits: the parking suspension signs last November. The two-day closure was extended across the week, so extensive was the decay discovered by engineers
Visits to the surface level car park beneath the Flyover reveal rust staining and damaged concrete on the underside of the structure.
In evidence to the London Assembly in September, TfL explained that salts used to keep the road safe in winter were corroding the steel bars that reinforce the concrete.
The latest warning follows engineering investigations reported by Inside Croydon last November.
TfL closed parts of the Wandle Road surface car park, directly beneath the Flyover, so engineers could examine the structure.
Parking restrictions initially expected to last two days were extended across the week,so extensive was the decay discovered by engineers.
Carl Eddleston, TfL’s director of streets and network operations, confirmed at the time that the Flyover needed refurbishment.
TfL’s investment committee papers also record six weeks of emergency lane closures in May and June 2025 to repair high-priority defects. This September, TfL made a temporary traffic order allowing overnight restrictions on part of Whitgift Street for further Flyover investigations.

Showing its age: the Wandle Road car park, under the Flyover, is used for regular safety checks on the structure
The proposed massive engineering project includes renewing the waterproofing and drainage, replacing the Flyover’s expansion joints and parapets and repairing concrete and other structural elements below deck. TfL says the work would extend the Flyover’s life by at least 25 years.
The Hammersmith Flyover, which is of similar vintage to Croydon,was closed in 2013 for a project that took two years and cost £100million.
TfL is seeking 85% of the estimated £30million cost from the Department for Transport, with construction pencilled in for April 2027 and completion by the end of March 2030. That timetable depends on funding. Croydon Council and the London Assembly’s transport committee have backed the bid.
An earlier TfL report had pencilled in a start in summer 2026 for the Flyover repairs. By March this year, TfL told Inside Croydon it was still completing design and planning. That timetable has slipped, and is unlikely to proceed without the government’s help.
BBC London has reported that TfL has identified 13 priority schemes across London, with a combined cost of more than £400million.

TfL is warning warned that without major repairs Vauxhall Bridge could also have to close to heavy vehicles, including buses and fire engines, within two to four years.
The covid pandemic, and the millions squandered on vanity projects by Boris Johnson when he was London Mayor has left TfL with inadequate funds for capital works and maintenance on its major roads and infrastructure.
Works have since been conducted on the A40.
TfL’s investment planning director, David Rowe, told BBC London that the authority spends about £30million a year renewing its structures. Across the transport network, including roads and the Tube, the BBC reported a maintenance backlog is estimated at £6.5billion.
The Department for Transport’s £1billion Structures Fund is open to bids from across England. Transport minister Justin Madders yesterday told Parliament that officials were still reviewing applications and hoped to announce the outcome before the end of the year.
A D V E R T I S E M E N T
PAID ADS: To advertise your services or products to our 10,000 weekday visitors to the site, as featured on Google News Showcase, email us inside.croydon@btinternet.com for our unbeatable ad rates
- If you have a news story about life in or around Croydon, or want to publicise your residents’ association or business, or if you have a local event to promote, please email us with full details at inside.croydon@btinternet.com
As featured on Google News Showcase
- Our comments section on every report provides all readers with an immediate “right of reply” on all our content. Our comments policy can be read by clicking here
Inside Croydon is a member of the Independent Community News Network


Back in the early days of Westfield (or whatever they are calling themselves this month?) blighting Croydon town centre, TfL had a plan to destroy Waddon by introducing flyovers at the Fiveways junction so that they could get more shoppers in fume-belchers to and from the big, new shopping centre in Croydon. If they had got away with that (to complete the destruction of central Croydon which was begun by Croydon Council planners in the 1960s with the ill-fated and incomplete motorway ring-road), would TfL have been happy to fix the Croydon flyover THEN ?
The street lights on the Croydon Flyover have been missing for over 7 years, not that piss-poor Perry or our local London Assembly Member, sweary Neil Garratt have noticed. High time the horrible thing was pulled down; it’s not needed and the money and land could be put to much better uses
Might Inside Croydon’s podcasts have to move out from “Under the Flyover”?